AACE International AACE Certification CCP Question # 6 Topic 1 Discussion

CCP Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost variance (CV)?


A.

BCWP-ACWP = 105,000-110,000 = -5,000


B.

ACWP-BCWP = 110,000-105,000 = 5,000


C.

BCWS-ACWP = 100,000-110,000 = -10,000


D.

ACWP-BCWS = 110,000-100,000 = -10,000