AACE International AACE Certification CCP Question # 12 Topic 2 Discussion

CCP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

When analyzing a precedence diagram schedule, the "backward pass"


A.

Allows total float to be calculated


B.

Determines the duration of each activity


C.

Calculates the earliest allowable start and finish times for the activities in the schedule


D.

Allows activities to finish as soon as all their 'predecessor' relationships are satisfied