AACE International AACE Certification CCP Question # 21 Topic 3 Discussion

CCP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?


A.

1


B.

1.04


C.

0.89


D.

0.96