Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam CCP All Questions
Exam CCP All Questions

View all questions & answers for the CCP exam

AACE International AACE Certification CCP Question # 27 Topic 3 Discussion

CCP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?


A.

Project is ahead of schedule, but over budget


B.

Project is behind schedule, but over budget


C.

Project is behind schedule, but under budget


D.

Project is ahead of schedule, but under budget


Get Premium CCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.