Aside from predecessors, resource manager assignments, and system administrator settings, what are three prerequisites for using the Resource Planner and Workload Balancer? (Choose three.)
Objective: Identify prerequisites for using the Resource Planner and Workload Balancer.
Prerequisites:
Prerequisite 1: Job Roles assigned to Tasks
Explanation: Assigning job roles helps in resource allocation and planning within the Resource Planner and Workload Balancer.
Prerequisite 2: Task Planned Hours greater than zero
Explanation: Tasks need to have planned hours to be considered in the resource planning and workload balancing.
Prerequisite 3: Task Durations greater than zero
Explanation: Tasks must have a duration set to be included in the workload calculations.
[: These prerequisites are detailed in the Workfront documentation on resource management and task settings., , ]