A facility owner is considering installing a new chiller. The installed project cost will be $300,000. The annual savings from the energy-saving project will be $45,000 for the 20-year life of the chiller. If an energy-service company requires a minimum 20% return on investment (pre-tax), will the energy-service company agree to finance this project?


A.

Yes


B.

No