AGA Government Financial Manager GAFRB Question # 18 Topic 2 Discussion

GAFRB Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

A state grant will reimburse a city for 40% of the architectural, construction and project management costs to build an annex to a city building. A city employee, who is paid salary and benefits of 510,000 a month, works half-time on the project for six months.

The city reports the following project budgeted and actual costs:

Purpose Budget Actual

Architectural fees $ 100.000 $ 90,000

Construction costs $10,500,000 $10,000,000

Based upon the above information, what is the amount of allowable costs that the state will reimburse the city on the grant?


A.

$4.048.000


B.

$4.060.000


C.

$4,252,000


D.

$4.264.000