According to API 936, theinstallation contractor must secure prior written approval or agreement from the ownerregarding all details of the installation. This includes procedures for curing, dryout, anchoring, repairs, and quality control. The owner or their authorized representative is the ultimate authority for project specification conformance.
[Reference:, API Std 936, Section 4.1 β βThe installation contractor shall obtain agreement from the owner for all installation procedures and requirements.ββ, ]