A company has a demand for 30 units of A, 40 units of B, and 50 units of C. These products are scheduled to run daily in batches of 10 as follows: ABC, ABC, ABC, CBC. What is this scheduling

technique called?


A.

Mixed-model


B.

Matrix


C.

Synchronized


D.

Line balancing