Question #: 31
Topic #: 5

Customer demand is 120 units per week. The company works on a 9-hour shift per day, 5-day per week basis. Each shift has a ½-hour lunch break and two 15-minute coffee breaks. The cycle time is 12 minutes. To meet demand, production must occur at the rate of one unit every:


A.

12 minutes.


B.

20 minutes.


C.

22.5 minutes.


D.

28 minutes.