APM Project Fundamentals Qualification APM-PFQ Question # 1 Topic 1 Discussion

APM-PFQ Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

What is a visual representation of a project's planned activities against a calendar called?


A.

a Gantt chart.


B.

a critical path network.


C.

a product flow diagram.


D.

a Pareto chart.