APM Project Fundamentals Qualification APM-PFQ Question # 4 Topic 1 Discussion

APM-PFQ Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

Which one of the following statements is true?


A.

Business-as-usual activities cannot be improved.


B.

Business-as-usual activities are more difficult to manage than projects.


C.

Projects are transient endeavours that bring about change to business-as-usual.


D.

A project is always the starting point for operation refinement.