APM Project Fundamentals Qualification APM-PFQ Question # 92 Topic 10 Discussion

APM-PFQ Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

Estimating by using historical information is known as:


A.

comparative estimating.


B.

parametric estimating.


C.

bottom-up estimating.


D.

strategic estimating.