APM Project Fundamentals Qualification APM-PFQ Question # 106 Topic 11 Discussion

APM-PFQ Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

Which one of the following is the best reason for splitting a project into phases?


A.

For team members to reflect on their performance during a phase.


B.

For the project manager to take a break between phases.


C.

It creates a decision point for continuing the project.


D.

In order for the plan to be updated regularly.