APM Project Fundamentals Qualification APM-PFQ Question # 110 Topic 12 Discussion

APM-PFQ Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

Which one of the following statements about the project management plan (PMP) is FALSE?


A.

The PMP acts as a contract between the Project Manager, the project team and the sponsor.


B.

The PMP defines the baselines for the project upon which changes are considered.


C.

The PMP, once defined, will remain unchanged throughout the project.


D.

The PMP is used as a reference document for managing the project.