Question #: 119
Topic #: 12

While providing support to the project and attending a risk management workshop, the following statements were noted. Which one of these could be considered as a risk to a project?


A.

We have never done a project of this kind before.


B.

We might not have sufficient people with the right experience to undertake the project.


C.

We always find that design verification takes longer than planned.


D.

We have never worked in that country before.