APM Project Fundamentals Qualification APM-PFQ Question # 122 Topic 13 Discussion

APM-PFQ Exam Topic 13 Question 122 Discussion:
Question #: 122
Topic #: 13

One purpose of risk management is to:


A.

adapt the plan to resolve problems.


B.

minimise threats and maximise opportunities.


C.

continually improve the project teams' efficiency.


D.

manage variations in a controlled way