APM Project Fundamentals Qualification APM-PFQ Question # 126 Topic 13 Discussion

APM-PFQ Exam Topic 13 Question 126 Discussion:
Question #: 126
Topic #: 13

Which one of the following statements is correct?


A.

Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.


B.

Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.


C.

Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.


D.

Quality planning enables the project manager to manage the trade-off between customer expectations and budget.