APM Project Fundamentals Qualification APM-PFQ Question # 127 Topic 13 Discussion

APM-PFQ Exam Topic 13 Question 127 Discussion:
Question #: 127
Topic #: 13

As part of the risk management process the capture of threats and

opportunities to the project objectives are referred to as:


A.

risk assessment.


B.

risk avoidance.


C.

risk exposure.


D.

risk identification.