APM Project Fundamentals Qualification APM-PFQ Question # 20 Topic 3 Discussion

APM-PFQ Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

Who is primarily responsible for configuration management in the project?


A.

Project manager,


B.

Risk manager.


C.

Quality manager.


D.

The project team.