APM Project Fundamentals Qualification APM-PFQ Question # 31 Topic 4 Discussion

APM-PFQ Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

The risk management process is concerned with managing which of the following?


A.

Threats and opportunities.


B.

Risks and issues.


C.

Issues that have arisen.


D.

Risk events with negative impact.