Question #: 40
Topic #: 5

The accuracy of an estimate should:


A.

decrease as a project progresses through its lifecycle.


B.

increase as a project progresses through its lifecycle.


C.

stay constant throughout the project.


D.

vary independently of where the project is in its lifecycle