What is the likely decision to arise from the response stage of the risk management process?
Whether to proceed with the project or recommend termination.
Whether the process being used is robust enough for the project being undertaken.
Whether to proactively invest to bring the exposure to risk within tolerable levels.
Whether to use brainstorming or a workshop to decide on the best response.