APM Project Fundamentals Qualification APM-PFQ Question # 48 Topic 5 Discussion

APM-PFQ Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

Which one of the following statements is true?


A.

Risk events always have beneficial effects on the project.


B.

Risk events can have either beneficial or detrimental effects on the project.


C.

Risk events always have detrimental effects on the project.


D.

Risk events have neither beneficial nor detrimental effects on the project.