APM Project Fundamentals Qualification APM-PFQ Question # 63 Topic 7 Discussion

APM-PFQ Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

The business case is owned by the project:


A.

manager.


B.

sponsor.


C.

steering group (board).


D.

senior user.