Which one of these categories would best represent project issues?


A.

Uncertain events that may or may not occur.


B.

Opportunities that occur through change control.


C.

Problems that the project manager has to deal with on a day-to-day basis.


D.

Threats to the project which cannot be resolved by the project manager.