Which of the following defines the term 'issue'?


A.

A problem which is now or is about to breach delegated tolerances for work on a project or programme.


B.

A problem which occurs on a day-to-day basis which could have an immediate impact on a project.


C.

A problem which has the potential to impact on the achievement of specific project objectives.


D.

A problem which can only be resolved by a project manager and within the project team