APM Project Fundamentals Qualification APM-PFQ Question # 85 Topic 9 Discussion

APM-PFQ Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

One of the main purposes of dividing a project into life cycle phases is to:


A.

break the work into controllable blocks in terms of effort and size.


B.

ensure the processes are properly maintained.


C.

ensure that the workforce is certain of their individual roles.


D.

provide a means Of producing overall project cost estimates.