APM Project Fundamentals Qualification APM-PFQ Question # 87 Topic 9 Discussion

APM-PFQ Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

Which of these is likely to occur if the scope is poorly defined?

1. Additional time spent in the concept phase

2. Scope creep

3. Budget over/under runs

4. Scheduling problems


A.

1, 2 and 3


B.

1, 2 and 4


C.

1, 3 and 4


D.

2, 3 and 4