APM Project Fundamentals Qualification APM-PFQ Question # 89 Topic 9 Discussion

APM-PFQ Exam Topic 9 Question 89 Discussion:
Question #: 89
Topic #: 9

A project stakeholder could best be described as:


A.

A member of the sponsoring organisation's board of directors.


B.

A key player who is seeking to maximize control over the project


C.

A person or group who has an interest in or is impacted by the project.


D.

A project team member who has the skills necessary to deliver the project