A Timebox Plan is updated at the Daily Start-ups. These daily meetings allow the team to review progress, discuss any issues, and make necessary adjustments to the plan. Regular updates ensure that the project stays on track and that any deviations are addressed promptly, facilitating smooth and efficient progress towards the Timebox objectives.
References:
AgilePM Foundation Handbook
"Scrum: The Art of Doing Twice the Work in Half the Time" by Jeff Sutherland