Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam AgilePM-Practitioner All Questions
Exam AgilePM-Practitioner All Questions

View all questions & answers for the AgilePM-Practitioner exam

APMG-International AgilePM AgilePM-Practitioner Question # 7 Topic 1 Discussion

AgilePM-Practitioner Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?


A.

Refuse to discuss any detailed requirements in the early phases.


B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.


C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.


D.

Capture the Marketing Director's requirements in detail but leave the

input of others until later in the project.


Get Premium AgilePM-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.