Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam AgilePM-Practitioner All Questions
Exam AgilePM-Practitioner All Questions

View all questions & answers for the AgilePM-Practitioner exam

APMG-International AgilePM AgilePM-Practitioner Question # 8 Topic 1 Discussion

AgilePM-Practitioner Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?


A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.


B.

Accept that members of the Solution Development Team will be

inconsistent.


C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.


D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.


Get Premium AgilePM-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.