Question #: 12
Topic #: 2

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?


A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.


B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.


C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.


D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.