AgilePM-Practitioner Exam Topic 2 Question 23 Discussion:
Question #: 23
Topic #: 2

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?


A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.


B.

The Solution Development Team should commence understanding and delivering the new requirement.


C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.


D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.