How should the Project Manager encourage the contractors to turn up on time?
Place a penalty clause on all contractors for late arrival.
Appoint Team Leaders to each of the electrical and plumbing teams.
Encourage open and honest communication to re-establish an environment of trust.
Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.