APMG-International AgilePM AgilePM-Practitioner Question # 26 Topic 2 Discussion

AgilePM-Practitioner Exam Topic 2 Question 26 Discussion:
Question #: 26
Topic #: 2

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.

Is this an appropriate action related to acceptance criteria?


A.

Yes, because the new requirement needs to be understood, built and delivered in this Timebox.


B.

Yes, because the Local Planning Authority Officer owns the justification for the new requirement.


C.

No, because this new requirement would NOT be included in the original Prioritised Requirements List and therefore does NOT need acceptance criteria to be defined.


D.

No, because the Business Visionary is responsible for defining acceptance criteria.