APMG-International AgilePM AgilePM-Practitioner Question # 30 Topic 3 Discussion

AgilePM-Practitioner Exam Topic 3 Question 30 Discussion:
Question #: 30
Topic #: 3

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?


A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.


B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.


C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.


D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.