Question #: 31
Topic #: 3

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?


A.

Marketing Director, in the role of Business Visionary.


B.

Team Leader.


C.

Project Manager and Architect, in the role of Technical Co-ordinator.


D.

Architecture Angels' Senior Management Team.