What strategy should be used to handle deviations found at the design development gate?


A.

Update the design documents to reflect minor cosmetic changes only


B.

Carry any unresolved issues to the construction phase


C.

Ignore deviations that do not affect the project's final delivery date


D.

Reassess the project's design elements against the original quality objectives