Which of the following is the most effective way for a construction quality manager to review an 'action' submittal to ensure alignment with the project's quality plan?


A.

Approve the submittal based on cost-effectiveness.


B.

Prioritize speed of approval to keep the project on schedule.


C.

Verify the submittal meets all specified standards and requirements.


D.

Involve subcontractors in the review process with regular oversight.