ASQ certification CCQM Question # 29 Topic 3 Discussion

CCQM Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

When a project faces significant scope changes, including the addition of new features halfway through, how should a Construction Quality Manager evaluate and prioritize inspections?


A.

Prioritize inspections based on the original project plan and impact on schedule.


B.

Focus inspections and testing on new project elements, instead of on established parts of the construction.


C.

Concentrate inspections primarily on areas where the most resources have been allocated.


D.

Reassess and prioritize inspections based on the new elements' criticality and their potential impact on project integrity.