Which of the following approaches would be most effective when updating the risk-based inspection strategy due to an unexpected change in project requirements (e.g., the need to use a different type of insulation material)?


A.

Continue with the existing inspection plan while closely monitoring for any visible issues.


B.

Postpone non-critical inspections until the impact of the change is fully evaluated.


C.

Assess the new material's specifications and integrate relevant tests into the inspection strategy.


D.

Reduce the frequency of inspections to accommodate the updated project schedule.