AVIXA Communications Certifications CTS Question # 83 Topic 9 Discussion

CTS Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

Which document is used to clarify a project design issue?


A.

change order


B.

progress report


C.

request for change


D.

request for Information