CIMA Management E2 Question # 13 Topic 2 Discussion

E2 Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Which of the following is NOT designed to deal with risk and uncertainty when planning for time?


A.

Project evaluation and review


B.

Resource histogram


C.

Buffering


D.

Scenario Planning