There are many implications for an organisation when using PRINCE 2 for managing projects. Which of the following statements are correct?
The Project Manager can make decisions independently without the approval of the board
The Project Manager must follow a restricted step by step procedure
All six processes and the many sub processes must be followed
Project staff must operate under a strictly managed and controlled regime
All actions must be within the bounds of agreed project objectives and scope