A project team is engaged in a risk assessment process prior to the execution of a major project. One risk is assessed to be of low impact but medium likelihood (probability). In these circumstances the appropriate response is:
A.
Accept the risk, but monitor closely
B.
Negotiate the transfer of the risk to a third party