Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam E2 All Questions
Exam E2 All Questions

View all questions & answers for the E2 exam

CIMA Management E2 Question # 42 Topic 5 Discussion

E2 Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

Many companies use Critical Path Analysis (CPA) to manage projects.

 

Which TWO of the options below could be identified from a CPA diagram? 


A.

The activities which need to be completed before the next activity can start.


B.

The resource usage variance for each activity.


C.

The activities which can't overrun without delaying the whole project.


D.

The probable time for each activity.


Get Premium E2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.