CIPS Level 4 Diploma in Procurement and Supply L4M4 Question # 17 Topic 2 Discussion

L4M4 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

Jack Green is planning to use competitive tendering to source a new component for a new product that the customer research department has been developing for the domestic market. Jack is intending to use an open tender process. Which of the following aspects must Jack consider if an open tender procedure is to be used?


A.

The bidders must be pre-qualified prior to invitation to tender


B.

There must be an adequate number of suppliers in the market


C.

The tender will only be advertised in marketing journals


D.

The price will be the only criterion for supplier selection