A manufacturing organisation has a large volume of raw material stock now viewed as redundant. Which of the following is the most appropriate process for the organisation?
A.
Scrap the stock as environmentally as possible and reorganise the warehouse
B.
Repackage and isolate the stock from the remaining stock to maximise usable space
C.
Ask the original supplier for potential return and credit or sell the stock
D.
Maintain the safety and security of the stock for potential future use